Technology Inceptions: Tesla to Start Delivering Model 3 to China Buyers in March  |  Technology Inceptions: ISRO Working on Chandrayaan-2 Launch for Next Month  |  Parent Interventions: Parents can influence kids' musical tastes  |  Parent Interventions: Discipline strategies to tackle misbehaviour  |  Science Innovations: New properties of sulphur atom   |  Science Innovations: Psychiatric diseases linked to molecular set-up  |  Cover Story: NURTURE AGRI-BUSINESS  |  Cover Story: A friend in weed Floating farms on weed islands   |  Rajagiri Round Table: Cultivate New Tech Farm Beckons Gen Next  |  Parent Interventions: Stronger Self-Regulation In Childhood to Boost Resilience  |  Parent Interventions: Youth with good relationships stand up against bullying  |  Technology Inceptions: Volvo & Skanska’s Electric Site Reduces Carbon Emissions By 98%  |  Technology Inceptions: ISRO Launches GSAT-7A Military Communications Satellite on Board GSLV-F11 Rocket  |  Cover Story: WHEN FOOD COMES CALLING  |  Cover Story: Yours Online, Kudumbashree  |  
  • Pallikkutam Magazine
  • Companion Magazine
  • Mentor
  • Smart Board

December 20, 2018 Thursday 12:31:12 PM IST
Volvo & Skanska’s Electric Site Reduces Carbon Emissions By 98%

Swedish car manufacturer Volvo and contracting giant Skanska, who teamed up to work on a “Electric Site” research project in October have declared the project a success and decided to extend it until the end the year.

After running for 10 weeks at Skanska’s Vikan Kross quarry, near Gothenburg in Sweden, the tests have shown a 98% reduction in carbon emissions, better than the 95% originally predicted. There was also a 70% reduction in energy costs and a 40% reduction in operator costs.

Volvo Construction Equipment is continuing to predict that the site will reduce the total cost of operations by 25%.

The project used electric transport for each stage of work at the quarry, including excavation, primary crushing and transportation. Three Volvo prototype vehicles were used: the HX2 autonomous battery-electric load carrier, LX1 hybrid and EX1 70-tonne, dual-powered, cable-connected excavator.

Uwe Müller, Electric Site’s chief project manager, said: “Over the last ten weeks, we’ve made incredible progress, learned a lot and seen huge potential in the Electric Site solutions environmental, efficiency, safety and cost benefits. In fact, we have decided that we want to learn more, so we will extend our test period with Skanska until the end of the year. 

“The results we have seen so far confirm that this research project is a step towards transforming the quarry and aggregates industry and creating emission-free quarries.”